Better late than never
as Chalk River restart
is postponed a few weeks
Faulty reactor instrumentation has led Atomic Energy of Canada Limited to push back the return-to-service date of the National Universal reactor by up to two weeks, the group said Wednesday.
"During the fuel reloading, it was determined that a specific set of reactor instrumentation, important to safe operation, was not responding as expected," the AECL said in a statement.
The Chalk River, Ontario-based NRU reactor is expected to be up and running again by August 10 or 15, the AECL said. The originally planned return-to-serve date was July 31.

Ad Statistics
Times Displayed: 109575
Times Visited: 6641 MIT labs, experts in Multi-Vendor component level repair of: MRI Coils, RF amplifiers, Gradient Amplifiers Contrast Media Injectors. System repairs, sub-assembly repairs, component level repairs, refurbish/calibrate. info@mitlabsusa.com/+1 (305) 470-8013
The AECL warned that "unforeseen operational issues" could always further extend the re-start date.