Over 1650 Total Lots Up For Auction at Five Locations - NJ Cleansweep 05/07, NJ Cleansweep 05/08, CA 05/09, CO 05/12, PA 05/15

Chalk River up by second week of August: AECL estimate

by Brendon Nafziger, DOTmed News Associate Editor | July 29, 2010
Better late than never
as Chalk River restart
is postponed a few weeks
Faulty reactor instrumentation has led Atomic Energy of Canada Limited to push back the return-to-service date of the National Universal reactor by up to two weeks, the group said Wednesday.

"During the fuel reloading, it was determined that a specific set of reactor instrumentation, important to safe operation, was not responding as expected," the AECL said in a statement.

The Chalk River, Ontario-based NRU reactor is expected to be up and running again by August 10 or 15, the AECL said. The originally planned return-to-serve date was July 31.
stats
DOTmed text ad

We repair MRI Coils, RF amplifiers, Gradient Amplifiers and Injectors.

MIT labs, experts in Multi-Vendor component level repair of: MRI Coils, RF amplifiers, Gradient Amplifiers Contrast Media Injectors. System repairs, sub-assembly repairs, component level repairs, refurbish/calibrate. info@mitlabsusa.com/+1 (305) 470-8013

stats
The AECL warned that "unforeseen operational issues" could always further extend the re-start date.